Manage BOP > Product assignment > Plant BOP process area planning
Assign target assemblies to a plant BOP
You can assign one or more target assemblies to a plant bill of process (BOP) in the High Level Planning page and then load them into the Process Planning page. This lets you work with the plant structure and the assembly structure data.
Procedure
Search for and open an existing work package and then navigate to the High Level Planning page.
Select a process from the BOP panel.
Assign target assemblies to the selected process by selecting an assembly from the Assembly panel and dragging it to the Target Assembly tab in the information panel.
A Target Assembly tab is displayed in the information panel below the BOP panel. If a target assembly is not assigned from the Assembly panel to the selected process in BOP panel, the target is inherited by default from the plant BOP root item.Select the process from the BOP panel, and navigate to the Process Planning page.
The plant BOP opens in a Process Planning page.
Results
The Process Planning page displays the target assembly from the High Level Planning page in the Target Assembly tab. The selected process is displayed in the Process panel.