Designing process structure > Creating operations and activities
Assign unclassified resources to an operation
Assign unclassified resources (such as tools) to an operation as follows:
Procedure
Open the My Teamcenter application and find the resource to be assigned to the operation.
Select the object and click the Copy button on the toolbar.
Open the Part Planner application.
Select the operation in the process structure.
Choose Edit→Paste Special.Teamcenter displays the Paste Special dialog box.
Select as component of selected assembly.
Enter the number of occurrences, quantity, and find number.
Select MEResource from the Occurrence Type list.
Click OK.
Note You did not make a copy of actual data when you performed the copy and paste functions. You merely copied an object that points to the data in the database.
Source: https://docs.sw.siemens.com/en-US/doc/282219420/PL20251212545240207.pmphelp/pmpa0505c · retrieved 2026-07-11