ManufacturingKnowledge

Manufacturing Process Planner general functionality > Comparing structures and propagating changes > Running an advanced accountability check

Roll up equivalent line quantities in accountability checks

If quantities in a set of source and target lines are different across those lines but add up to the same total, you can make them equivalent (a full match) in your final accountability check results.

Procedure

  1. Choose Tools→Accountability Check→Advanced Accountability Check.

  2. In the Advanced Accountability Check dialog box, click the Reporting tab.

  3. If it is not already enabled, select Report the selected check criteria.

  4. In the Display Options group, select the Multiple Match check box.

The Consider quantity rollup for multiple match check box is enabled.

  1. Select the Consider quantity rollup for multiple match check box .

The Multiple Match check box is disabled and quantities in the set of source and target lines that add up to the same total will now appear equivalent (a full match) when you run an advanced accountability check. Note Deselect Consider quantity rollup for multiple match to reenable the Multiple Match check box.

Related Topics

  • Setting up the accountability check

Source: https://docs.sw.siemens.com/en-US/doc/282219420/PL20251212545240207.mse/xid1119875 · retrieved 2026-07-11