Create and manage operations in PERT view

Use PERT and tree commands to work with operations in the Process Planning or High Level Planning pages.

Procedure

  1. If you have not done so already, search for and open an existing work package and navigate to the preferred page.

    When you work with operations in the PERT view in Process Planning, you can switch between the tree view and the PERT view to access all the commands at the operations level.

  2. (Optional) From the top right corner of the Process tab, click Sequence View .

    The PERT view, or sequence view, displays a pictorial representation of the processes. Note The Sequence View button is visible when operations or process resources exist under a station. If no process resources exist, the button opens a PERT view. If process resources exist, the button opens a PRI view.

  3. (Optional) Click Tree View to display the tree view.

    The Tree View lists processes in hierarchical order.

  4. Click Move Mode to move the PERT chart.

  5. Select the required process, then click Flow Creation Mode and drag to another process to create a flow sequence.

  6. Select the process you want to delete, then click Delete to delete the process.

Results

Note

Commands such as Set as Successor, Set as Predecessor, Clone, Submit to Workflow, and Create remain available in operations.