Edit activity start times and durations in the Operation Activities tab
Procedure
Expand the process hierarchy in the Process pane and select an operation.
Choose Open with→ Activities.
Double-click a Start or Duration value. The value becomes editable.Note The Calculated Start and Calculated Duration values cannot be changed.
Type a new value.
Click outside of the entry box to exit edit mode.The root activity's Duration is automatically recalculated using the new values.