Designing process structure > Creating operations and activities
Create operation activities using the Activities view
Each operation can have individual activities that break down the operation into steps describing in detail what is done as part of that operation. For example, a material procurement operation may include an activity to unload the material and another activity to move the material to a storage area. The activities are created as children of the operation.
Each activity is defined by its type, description, start time, and duration. An activity can also reference Teamcenter objects. This enables you to attach any forms to the activity that represent features and their associated tooling and instructions.
Note
You cannot create revisions of activities.
The cumulative time of all activities is recorded and charted on the Activities Gantt view.
Procedure
In the process structure view, select the operation to which you want to add an activity.
Choose Open With→Activities.Teamcenter opens the Activities view displaying all the activities belonging to the selected operation.
Select the parent activity for the new activity.
Click the Create New Activity button on the view toolbar.The New Activity dialog box is displayed.
Select the activity type. If there are many types to choose from, you can type a search filter to narrow your choices.
Click Next.
Enter the required information in the activity form. The information you enter here is dependent on your business needs. Mandatory fields are designated by a red star.
Click Finish to add the activity.
(Optional) After adding the activities, specify the desired sequence operation activity.
To create an activity from a template:
Procedure
In the structure view, select the operation to which you want to add an activity.
Choose Open With→Activities from the shortcut menu.
Select the parent object for the activity in the Operation Activities pane.
Choose File→New→From Template→Activity from Template.
Click the Find Template tab to search for an existing template, or select a template from the Favorite Templates pane.
Managing activity times with the Activities Gantt view
Select an activity template