ManufacturingKnowledge

Line balancing and detailed timing > Create a time study for process resources

Publish a time study

After you finalize a time study, you can publish it to update the existing plant bill of process (BOP).

Note

When you publish a time study, Easy Plan only updates the objects in the time study. All other objects in the plant BOP are unchanged.

Procedure

  1. If you have not done so already, search for an open a work package, and then navigate to the Process Planning page.

  2. In the Process panel select the process resource that contains the time study you want to publish and then click Show Time Studies.

  3. In the Time Studies panel select the time study you want to publish.

  4. Click the time study name, then select More and Time Study.
    Easy Plan opens the Time Study page.

  5. Verify that you opened the correct study and then click Publish from Study. Easy Plan publishes the time study, which overwrites the existing plant BOP.

Source: https://docs.sw.siemens.com/en-US/doc/282219420/PL20251212545240207.xid2214895/elu0206527794491 · retrieved 2026-07-11