Manage BOP > Product assignment > Plant BOP process area planning

Drag or copy resources to assign them to process stations

You can assign one or more resources to process stations, either by dragging or copying from available work package resources, or by copying from a manufacturing resource library (MRL) .

Prerequisites

To be able to assign resources to process stations, you must add the value Mfg0BvrProcessStation to the preference EP_AllowCopyPasteResourceOnTarget.

Procedure

  1. If you have not already done so, navigate to the Process Planning task page.

  2. From the Resources tab, select one or more resources from a station.

  3. Do any of the following to assign resources.

                 Drag the selected resources to one or more process
                     stations in the Process
                     panel.
                 Click  → Copy
                     , and in the Process panel, select a station and click Paste
                     .  
                 Copy
                     assigned resources from one process station to another process station.
                         In the Process panel, select the
                                 station from which you want to copy resources.
                         In the Information panel, on
                                 the Resources tab,
                                 select the resources that you want to copy and click  → Copy
                                 .
                         In the Process panel, select the
                                 station to which you want to paste the resources and click
                                     Paste
                                 .
                     
                 Copy resources from a manufacturing resource library
                         (MRL).
                         In the Information panel, in
                                 the Resources tab,
                                 right-click a resource and choose Classification Search.The Teamcenter Classification page is displayed in a new
                                 browser window.
                         Using the classification
                                     Class Navigator,
                                 locate, select, and copy the preferred MRL resources.Note 
                                 For more information, see the *Basic and Advanced Classification on
                                         Active Workspace - Usage* online help.
                             
                         Close the Classification page and in the
                                     Process panel of
                                     Process Planning
                                 task page, select a process station and paste the MRL resources
                                 assign them to that station.
                     
             
             In the Information panel, in the Resources tab, the
                 dragged or copied resources are displayed for the station selected in the
                     Process panel.
    