A product BOP containing a process with three operations is created, and the process is allocated to the plant BOP. After allocation, a new operation, new_operation_04, is added to the product BOP. In addition, a new operation, station-specific_operation_05, is added to the plant BOP only.

An accountability check is run with the following options.

This produces the following results.

The new operation in the product BOP, new_operation_04, is listed under the source in the Partial Match Details section, but the target is empty. In addition, the new operation that was added to the plant BOP, station-specific_operation_05 does not appear at all in the results, as the Skip processes and operations that are structure specific option was selected in the General tab when running the check.

Source: https://docs.sw.siemens.com/en-US/doc/282219420/PL20251212545240207.xid1364469/id1675462 · retrieved 2026-07-11