ManufacturingKnowledge

Line balancing and detailed timing > Assign operations from Product BOP to stations > Operations

Move operations to a process resource in a different station

You can move an operation to a process resource in another station. You may want to do this if one station exceeds the takt time, and another station is underutilized.

Note

You can also drag and drop operations to move them to a process resource in a different station.

  1. Open or navigate to a process area or process line that contains process stations.

  2. Click the Balancing tab.

  3. Select one or multiple operations and click Cut .

  4. Select a process resource of a station from the list and click Paste .