ManufacturingKnowledge

Authoring manufacturing process plans > 4D planning – visualizing construction over time

Update the process-task association

You can change the process-task association at any time in the Process – Task Association dialog box.

Procedure

  1. Open the Process – Task Association dialog box.

To open the dialog box from a schedule, right-click the task and choose Assignments→Process — Task Association.

To open the dialog box from a process structure, right-click a process and choose Link/Associate→Process — Task Association.

  1. Select the new process or task and click to add it to the relevant box.

  2. Click Associate.

Teamcenter associates the process and task and replaces any existing associations with the selected process-task association.

To remove the association between process and task, do one of the following:

  • Open the Process – Task Association dialog box and click Un-Associate All.

  • Choose Assignments→Un-Associate All from the shortcut menu.

Set up 4D planning

Source: https://docs.sw.siemens.com/en-US/doc/282219420/PL20251212545240207.mse/xid506472 · retrieved 2026-07-11