ManufacturingKnowledge

Manufacturing Process Planner general functionality > Comparing structures and propagating changes > Accountability check examples

Example: viewing an assignment mismatch

The following product BOP is linked to a plant BOP. After allocating processes and operations, a new part is assigned to the product BOP by logical designator, top;pos_05.

An accountability check is run between the product BOP and its associated plant BOP with the following settings.

  • Source inclusion rule: AccountabilityProcessAllNoAssign

  • Target inclusion rule: ACPlantBOPDerivedProcessesAndOps

The results are as follows.

By selecting the partial match line 000050 in the source and clicking the Equivalent Lines tab in the target, you can see that line 001269 is the equivalent allocated line in the plant BOP.

In the Partial Match section, on the Assignment tab, the logical assignments are listed under the source but there is one assignment missing under the target: the top;pos_05 logical assignment.

Source: https://docs.sw.siemens.com/en-US/doc/282219420/PL20251212545240207.mse/id1675461 · retrieved 2026-07-11