Over time, time data can change and it can become necessary to update the TiCon time elements contained in your structure.

Procedure

  1. Do one of the following to select the object to update:

Select a process or operation in the structure view.

Select an activity in the Activities section of the Time view.

  1. Choose Tools→TiCon→Update from the main toolbar.

Teamcenter displays the TiCon Update dialog box.

  1. If the time element in TiCon contains a substructure, specify the number of levels of structure that you want to include in the activity structure and click Start.

Tip You can use this option to remove levels from or add levels to a substructure by specifying fewer or more levels than you did when you created the activity or last performed an update.

Teamcenter compares all the time information in the activities belonging to the selected structure with the current time information for the associated time element in TiCon. If it finds differences, it lists them in the dialog box.

  1. (Optional) Navigate through the changes selecting each line. For each selected line, Teamcenter displays the potential change at the bottom of the dialog box.

  2. Click Update to apply the changes, or Cancel to close the dialog box without updating.