Verifying structure design > Modifying process plan data > Understand the Gantt
Create a flow
You can only create flows between processes or operations at the same level in a structure that have the same parent (sibling lines).
Do one of the following:
Create a flow between elements by selecting at least two bars in the Gantt chart and click .Teamcenter creates a flow between the elements in the order that you selected them.
Create a flow by dragging one bar to another in the representation pane.If, for example, you drag Process 1 to Process 2, Teamcenter creates a flow from Process 1 to Process 2.
Select the desired nodes in the tree structure in the navigation pane and click .Teamcenter creates a flow between the elements in the order that the nodes appear in the tree. Tip Teamcenter displays the names of the source and target elements in a tool tip on the flow.