Validating manufacturing process plans > Managing alternative planning projects
Quickly update moved elements in an alternative plant BOP
You can quickly update an alternative plant bill of process (BOP) when elements are moved in the production plant BOP. This example shows how to update an alternative BOP when operations are moved between processes.
Procedure
- Open the production plant BOP in which the operations were moved and the alternative plant BOP.
In this example, operation OPA2 has been moved from operation PRA to operation PRB.
- In the alternate BOP, right-click PRA and choose Propagate.
The operations are moved in the alternate BOP from PRA to PRB and match the production BOP.