Calculating start times based on calculated duration
When the calculated duration mode is turned on, the calculation of start times is based on the calculated duration of the predecessors. If calculated duration is off, the start times are calculated based on the duration of the predecessors.
Teamcenter always turns off the critical path mode when you change the calculated duration mode because the critical path most likely changes after the calculated duration mode is switched.