The following flows are created in the PERT view for the processes belonging to a product BOP.

The top level process, process_02, is allocated to a plant BOP, and then the flows in the product BOP are subsequently changed.

Now there is a discrepancy in the sequence of processes between the product BOP and the associated plant BOP. An accountability check is run between these two structures with the following options.

The check produces the following results.

In the partial match results, the source (product BOP) shows two predecessors for process_08 whereas in the target (the plant BOP), process_08 has only one predecessor, process_07.