Manage BOP > Product assignment > Viewing and analyzing consumption status data
Line balancing assignment status icons
On the Line Balancing page, assignment indications are based on the bill of process (BOP) line balancing scope. For example, if you are viewing a zone with 10 stations, the line balancing scope is the zone.
| (Blank) The operation is unassigned to any process area. | |
|---|---|
| The operation is assigned to a process area in the current line balancing scope. Click the icon to jump to the process area in the current scope and highlight the operation in the Operations list. | |
| The operation is consumed under other processes that are not in the current line balancing scope. Click the icon to jump to the process area where this operation is consumed. | |
| The operation is assigned to multiple process areas, including areas in the current line balancing scope and possibly in another line balancing scope. Click the icon to see a list of the process areas where the operation is assigned. In the example below, the operation is located in three process areas in the current scope and three in a different scope. | |
| The operation is assigned to multiple process areas. However, none of them are in the current line balancing scope. Click the icon to see a list of process areas where this operation is consumed. | |
| The operation has properties that were changed in the current scope of the plant BOP or the product BOP after allocation. This is a in-scope partial match warning. | |
| The operation has properties that were changed in another scope of the plant BOP or the product BOP after allocation. This is a out-of-scope partial match warning. | |
| The operation was deleted from the product BOP after it was allocated to the plant BOP. This is a missing in source error. |