ManufacturingKnowledge

Multi-BOM Management general functionality > Visualizing structures > Managing product and manufacturing information (PMI)

Filter assigned and unassigned PMI objects

If you have a large number of PMI objects in the product view and want to verify which are or are not assigned in the process view, you can filter them in the PMI Manager view.

Procedure

  1. Open the PMI Manager view from the product structure by right-clicking the line that includes the PMI objects shared with the process structure and choosing Open with→PMI Manager.

Tip If you already have a different PMI Manager view open, you can change to the product view by clicking in the PMI Manager view.

  1. In the process structure, select the structure that includes the same PMI objects.

  2. In the PMI Manager view, click Set selected process/operation as target process .

The process structure sets the scope of the command.

  1. Select Filter data based on assignment indication and choose Assigned or Unassigned.