Line balancing and detailed timing > Create process resources > Process resources and operators
Create a process resource in the plant BOP tree
You can create a process resource in the plant bill of process (plant BOP) tree and then assign operations to it. The process resource can be an operator or a machine.
Prerequisites
You must set the TCAllowedChildTypes value to Mfg0ProcResourceRevision. In addition, you must add TCAllowedChildTypes to the AWC_StartupPreferences in the Teamcenter rich client.
See the Preferences section in the Active Workspace Administration documentation for a description of preferences and how to set them.
Procedure
Search for and open an existing work package and then navigate to the Process Planning page.
Expand the assembly, select a station, and then click Create Process Resource . Note You must create the process resource from a process station. You cannot create the process resource from other objects within the product BOP.
In the Create Process Resource dialog box select the process resource type, then type a Name and click Create.
Teamcenter Easy Plan creates the process resource as a child of the station.(Optional) In the assembly, select the process resource you created and click Create Operation . Teamcenter Easy Plan creates the operation as a child of the process resource, and assigns that operation to the process resource.